Green Collar Job Training - Free

#

Course Title
100 Home
101 Introduction
102 FAQ Page
103 Course Catalog
104 Green World
105 Demand & Supply
106 Conservation Careers
107 Solar Careers
108 Wind Turbine Careers
109 Entrepreneurs
110 Employee or Employer?
200 Demand Management
201 Summary
202 Residential Energy Profile
203 Ten Conservation Rules
204 HVAC System
205 Kitchen Appliances
206 Water Heater
207 Lighting
208 Laundry Appliances
209 Calculating Savings
300 Renewable Technology
301 Solar Energy
302 Solar Collectors
303 Solar Water Heating
304 Stirling Engines
305 Basic AC-DC Electronics
306 Silicon Solar Panels
307 Thin Film Solar Panels
308 Wind Turbines
309 Inverters
310 Grid Tied and Off Grid
311 Solar Site Survey
312 Solar Site Diagram
313 Sun Path Chart
314 Site Survey Worksheet
315 Wind Turbine Site Survey
316 Wind Turbine Worksheet
400 Solar Thermal Design
401 Solar Heat Overview
402 System Configuration
403 Site Survey
404 SRCC Compliance
405 System Specification
406 Bill of Materials
407 System Installation
408 Solar Heat Incentives
409 Document Package
410 Future Products
500 Solar PV Design
501 Solar PV Overview
502 System Configuration
503 Site Survey
504 Grid Tied & Off Grid
505 System Specification
506 Bill of Materials
507 System Installation
508 Solar PV Incentives
509 Document Package
510 Future Products
600 Wind Turbine Design
601 Wind Turbine Overview
602 System Configuration
603 Site Survey
604 Grid Tied and Off Grid
605 System Specification
Green Collar Links
Green Collar Sponsors

 

Green Collar Careers - Solar PV System Installation

Once materials are on site solar PV systems installation take the following actions, not necessarily in this order:

  1. Constructing the racks and mounting system (if ground mounted this may require clearing the area of vegetation, putting down a ground cover such as gravel, and running trench to house.  Also rack system posts should be mounted in concrete).
  2. Mounting of the solar PV panels
  3. Cover solar panels with an opaque cloth to prevent them from generating electricity during the connection phase
  4. Aligning the solar PV panels to the elevation and azimuth (usually Solar Noon of the Spring/Fall Equinox)
  5. Mounting the Combiner Box
  6. Pulling the cable across routing path between the solar PV panels and the Combiner Box
  7. Mounting the DC Disconnect
  8. Pulling the cable across routing path between the Combiner Box and the DC Disconnect
  9. Mount the Inverter
  10. Pulling the cable across routing path between the DC Disconnect and Inverter
  11. Mounting the AC Disconnect
  12. Pulling the cable across routing path between the Inverter and AC Disconnect
  13. Installing the Grounding Rod
  14. Connect Grounding rod 1/0 cable to AC Disconnect, Inverter, DC Disconnect, Combiner Box, solar Panel Rack
  15. Install Surge Protector in AC Disconnect
  16. Install Lightning Arrestor in AC Disconnect
  17. Install Lightning Arrestor in Combiner Box
  18. Connect AC Disconnect to Inverter
  19. Connect Inverter to DC Disconnect and switch disconnect off
  20. Connect DC Disconnect to Combiner Box
  21. Check that solar PV panels are covered to prevent potential electrocution
  22. Connect DC Disconnect to Solar Panels
  23. Interconnect DC panels
  24. Double check all wiring runs are neat, properly dressed, and out of exposure to the elements
  25. Remove cloth covering on solar panels
  26. Check voltages at Combiner Box - ALL INPUTS AND OUTPUTS
  27. Resolve any voltage/connection issues to solar PV panels
  28. Read the Inverter Instructions to perform any initial power up instructions!
  29. Switch on DC Disconnect
  30. Check Inverter output and monitoring operations and perform any initialization tasks per the Inverter Manual
  31. Switch off the DC Disconnect
  32. Install the solar PV Power Meter - Utility may require outdoor mounting!
  33. Connect the solar PV Power Meter to the Inverter
  34. Switch off any major home appliances such as HVAC systems, dishwashers, TV's, PC's.  Its recommended to pull every plug in the home including the refrigerator - just in case you happened to get the 1 in a million defective Inverters!)
  35. Switch off the Main home Power Panel - usually pulling the two main breakers - verify there is no Utility AC power to the panel!
  36. Connect the cable from the AC Disconnect and the AC Main Power Panel
  37. Leaving the AC Main Utility Power off, switch on the DC Disconnect
  38. Switch on the AC Disconnect
  39. Observe the AC voltages at the Inverter
  40. Observe the L1, L2, and neutral voltages on the AC Main Panel
  41. This test will need to be run during a high output solar time. Switch on approximately 25% of the load generated from the solar panel and note any voltage drops on L1, L2 and neutral. 
  42. After 30 minutes (or per Inverter instructions) load the system to about 75% output and note voltage drops.  Inverter Manual will have clear instructions on this.
  43. Shut off load appliances.
  44. Switch AC Disconnect off
  45. Reconnect Utility power at AC Main Panel
  46. Switch AC Disconnect on
  47. Note reading on utility power meter and solar PV power meter and time
  48. Allow to run for 15 minutes and recheck meters.  Reading on outputs should match if the house loads are all off.
  49. Reconnect all unplugged devices in home
  50. Final inspection of system